Filters
Question type

Study Flashcards

The sum of times of the longest path in a network indicates expected project completion time, and the activities represent the critical activities.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Duration Estimate (Days)  Start  Finish  Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 1291521 B 13132123 C 246918 D 25233547 E 35192627 F 46232941 G 56142026 H 67258\begin{array}{r} \text { Duration Estimate (Days) }\quad \quad \quad \quad \\\begin{array}{lccccc} & \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 9 & 15 & 21 \\\text { B } & 1 & 3 & 13 & 21 & 23 \\\text { C } & 2 & 4 & 6 & 9 & 18 \\\text { D } & 2 & 5 & 23 & 35 & 47 \\\text { E } & 3 & 5 & 19 & 26 & 27 \\\text { F } & 4 & 6 & 23 & 29 & 41 \\\text { G } & 5 & 6 & 14 & 20 & 26 \\\text { H } & 6 & 7 & 2 & 5 & 8\end{array}\end{array} What is the estimated expected (mean) time (in weeks) for project completion?

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Duration Estimate (Days)  Start  Finish  Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 1291521 B 13132123 C 246918 D 25233547 E 35192627 F 46232941 G 56142026 H 67258\begin{array}{r} \text { Duration Estimate (Days) }\quad \quad \quad \quad \\\begin{array}{lccccc} & \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 9 & 15 & 21 \\\text { B } & 1 & 3 & 13 & 21 & 23 \\\text { C } & 2 & 4 & 6 & 9 & 18 \\\text { D } & 2 & 5 & 23 & 35 & 47 \\\text { E } & 3 & 5 & 19 & 26 & 27 \\\text { F } & 4 & 6 & 23 & 29 & 41 \\\text { G } & 5 & 6 & 14 & 20 & 26 \\\text { H } & 6 & 7 & 2 & 5 & 8\end{array}\end{array} What is the critical path for this project network?

Correct Answer

verifed

verified

Events 1-2...

View Answer

Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time (in days) is approximately:


A) 5.
B) 6.
C) 7.
D) 8.
E) 9.

F) A) and C)
G) B) and D)

Correct Answer

verifed

verified

What is the probability that this project will take more than 10 weeks to complete if the activity means and standard deviations are as shown below?  Activity  Mean  Std.Dev. 125123411381\begin{array} { l c c } \text { Activity } & \text { Mean } & \text { Std.Dev. } \\\hline 1 - 2 & 5 & 1 \\2 - 3 & 4 & 1 \\1 - 3 & 8 & 1\end{array}

Correct Answer

verifed

verified

Prob(duration exceed...

View Answer

A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:


A) 7.0.
B) 7.5.
C) 8.0.
D) 8.5.
E) 10.0.

F) C) and E)
G) None of the above

Correct Answer

verifed

verified

A hierarchical (vertical) listing of what must be done during a project is called matrix.

A) True
B) False

Correct Answer

verifed

verified

Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of six. Activity 6-7 has an expected time of seven and an ES time of seven. Activity 7-8 has an expected time of 10. The ES for activity 7-8 is:


A) 11.
B) 14.
C) 21.
D) 24.
E) 25.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

A disadvantage of activity-on-node diagrams is the occasional need for dummy activities.

A) True
B) False

Correct Answer

verifed

verified

A method used for establishing a logical framework for identifying the required activities for the project is called:


A) work breakdown structure.
B) PERT.
C) planning matrix.
D) crashing.
E) critical path analysis.

F) A) and E)
G) A) and C)

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B  A  C, D 445056 B  D 456075 C  E 424548 D  F 314049 E  F 273639 F  End 587082\begin{array}{l}\begin{array} { l c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 44 & 50 & 56 \\\text { B } & \text { D } & 45 & 60 & 75 \\\text { C } & \text { E } & 42 & 45 & 48 \\\text { D } & \text { F } & 31 & 40 & 49 \\\text { E } & \text { F } & 27 & 36 & 39 \\\text { F } & \text { End } & 58 & 70 & 82\end{array}\end{array} What is the estimated standard deviation in the time for activity E?


A) 1 days
B) 2 days
C) 3 days
D) 4 days
E) 5 days

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Many activities have slack time; if we add these slack times together, this represents the potential improvement in early completion for the project.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not true about the use of dummy activities in project networking?


A) They preserve the separate identities of activities.
B) They clarify precedence relationships among activities.
C) They have an activity time equal to zero.
D) They have an activity time variance equal to zero.
E) They are used in activities-on-nodes (AON) network diagrams.

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

A project is represented by the following diagram: A project is represented by the following diagram:   The expected duration of this project is: A)  13. B)  15. C)  20. D)  52. E) 81. The expected duration of this project is:


A) 13.
B) 15.
C) 20.
D) 52.
E) 81.

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Duration Estimates (Days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  U, V  U  W 355065 V  W, X 284052 W  Z 263544 X  Y 284052 Y  Z 262938 Z  End 366084\begin{array}{r}\text { Duration Estimates (Days) }\quad\quad\quad\\\begin{array} { l c c c c } \text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { U, V } & - & - & - \\\text { U } & \text { W } & 35 & 50 & 65 \\\text { V } & \text { W, X } & 28 & 40 & 52 \\\text { W } & \text { Z } & 26 & 35 & 44 \\\text { X } & \text { Y } & 28 & 40 & 52 \\\text { Y } & \text { Z } & 26 & 29 & 38 \\\text { Z } & \text { End } & 36 & 60 & 84\end{array}\end{array} What is the estimated slack time for activity W?


A) 0 days
B) 25 days
C) 35 days
D) 45 days
E) 85 days

F) B) and C)
G) All of the above

Correct Answer

verifed

verified

The latest starting time for an activity is equal to the latest finish time minus the activity time.

A) True
B) False

Correct Answer

verifed

verified

Gantt charts are most closely associated with


A) JIT.
B) PERT.
C) MRP.
D) MRPII.
E) Six Sigma.

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

Which of the following is not characteristic of good risk management?


A) estimating the likelihood of chance events occurring
B) planning to eliminate chance events
C) identifying potential chance events
D) formulating contingency plans for chance events
E) analyzing the consequences of chance events

F) A) and E)
G) All of the above

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B  A  C, D 445056 B  D 456075 C  E 424548 D  F 314049 E  F 273639 F  End 587082\begin{array}{l}\begin{array} { l c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 44 & 50 & 56 \\\text { B } & \text { D } & 45 & 60 & 75 \\\text { C } & \text { E } & 42 & 45 & 48 \\\text { D } & \text { F } & 31 & 40 & 49 \\\text { E } & \text { F } & 27 & 36 & 39 \\\text { F } & \text { End } & 58 & 70 & 82\end{array}\end{array} What is the estimated expected (mean) time for project completion?


A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days

F) None of the above
G) A) and C)

Correct Answer

verifed

verified

Showing 21 - 40 of 137

Related Exams

Show Answer