Consider the following work breakdown structure:  Time Estimates (wks)   Start  Finish  Activity  Node  Node t0tmtp A 12112029 B 23258 C 24183042 D 3471013 E 14314043\begin{array}{r}{\text { Time Estimates (wks) }} \\\begin{array}{lccccc}& \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } \quad\quad& \text { Node } \quad\quad& \mathrm{t}_{0} \quad\quad& \mathrm{t}_{\mathrm{m}} \quad& \mathrm{t}_{\mathrm{p}} \quad\\\hline \text { A } & 1 & 2 & 11 & 20 & 29 \\\text { B } & 2 & 3 & 2 & 5 & 8 \\\text { C } & 2 & 4 & 18 & 30 & 42 \\\text { D } & 3 & 4 & 7 & 10 & 13 \\\text { E } & 1 & 4 & 31 & 40 & 43\end{array}\end{array} What is the estimated expected (mean) time for project completion?


A) 35 weeks
B) 39 weeks
C) 50 weeks
D) 104 weeks
E) 105 weeks

F) A) and D)
G) All of the above

Correct Answer

verifed

verified

Although PERT and CPM were originally developed for somewhat different types of projects, they are now nearly identical in terms of analysis and procedures.

A) True
B) False

Correct Answer

verifed

verified

A project has the activities and activity times (days) listed below. Determine the probability that the project will require more than 15 days from start to finish.  Activity  Exp.Time  St.Dev 1261.312462.701371.003460.00\begin{array} { l l l } \text { Activity } & \text { Exp.Time } & \text { St.Dev } \\\hline 1 - 2 & 6 & 1.31 \\2 - 4 & 6 & 2.70 \\1 - 3 & 7 & 1.00 \\3 - 4 & 6 & 0.00\end{array}

Correct Answer

verifed

verified

The probability of t...

View Answer

Consider the project depicted by the following A-O-A diagram: Consider the project depicted by the following A-O-A diagram:   What is the probability that this project's duration will exceed 8.5 weeks? What is the probability that this project's duration will exceed 8.5 weeks?

Correct Answer

verifed

verified

None...

View Answer

Prepare a crashing plan for the following project that will reduce the project duration by three weeks.  Activity  Normal  Time (week)  Cost for  First Crash  Cost for  Second Crash 124121524515151351012344894562020563111467512135771516\begin{array} { l c c c } \text { Activity } & \begin{array} { c } \text { Normal } \\\text { Time (week) }\end{array} & \begin{array} { c } \text { Cost for } \\\text { First Crash }\end{array} & \begin{array} { c } \text { Cost for } \\\text { Second Crash }\end{array} \\\hline 1 - 2 & 4 & 12 & 15 \\2 - 4 & 5 & 15 & 15 \\1 - 3 & 5 & 10 & 12 \\3 - 4 & 4 & 8 & 9 \\4 - 5 & 6 & 20 & 20 \\5 - 6 & 3 & 11 & 14 \\6 - 7 & 5 & 12 & 13 \\5 - 7 & 7 & 15 & 16\end{array}

Correct Answer

verifed

verified

First crashed activity is 5-6 for a cost of 11. This reduces overall duration to 22 weeks but creates two critical paths. There are two ways a second week can be crashed out of this project. Option 1 is to crash activity 4-5 by one week for a cost of 20. The other is to crash activities 3-4 (cost = 8) and 6-7 (cost = 12). For the third one-week reduction, activity 4-5 must be crashed, for a cost of 20.

There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to:


A) 2.
B) 4.
C) 8.
D) 16.
E) 64.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

To _____ an activity means to shorten the time it will take.


A) speed
B) fund
C) crash
D) aggregate
E) matrix

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The higher the node number, the longer the activity will take.

A) True
B) False

Correct Answer

verifed

verified

Activity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 15 days. Estimate its expected time and standard deviation.

Correct Answer

verifed

verified

None...

View Answer

Consider the following work breakdown structure:  Start  Finish  Duration (Days)   Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 12415059 B 13546066 C 24587082 D 34324144\begin{array}{cccccc}&\text { Start }&\text { Finish }&&\text { Duration (Days) } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 41 & 50 & 59 \\\text { B } & 1 & 3 & 54 & 60 & 66 \\\text { C } & 2 & 4 & 58 & 70 & 82 \\\text { D } & 3 & 4 & 32 & 41 & 44\end{array} What is the probability that this project will be completed within 130 days?


A) .8413
B) .90
C) .9544
D) .9772
E) .9987

F) C) and D)
G) None of the above

Correct Answer

verifed

verified

A Gantt chart is built using established precedence relationships.

A) True
B) False

Correct Answer

verifed

verified

Which of the following would probably not involve the use of PERT?


A) planning and constructing a new city hall
B) developing an advertising campaign for a new product
C) designing and constructing a subway system
D) writing a poem
E) preparing for the visit of a foreign dignitary

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

If two consecutive activities on the same path each have two days of activity slack, this means that each of them can be delayed by two days without delaying the project.

A) True
B) False

Correct Answer

verifed

verified

When developing probabilistic estimates of project duration, it is necessary to know which of the following?


A) the mean and variance of every activity
B) the mean and variance of activities on the critical path
C) the standard deviation of activities on the critical path
D) each activity's probability of completion
E) the distribution of activity times

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B, C  A  D 385062 B  E 9099108 C  End 85100115 D  F 192531 E  End 91100115 F  End 626568\begin{array}{l}\begin{array} { c c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B, C } & - & - & - \\\text { A } & \text { D } & 38 & 50 & 62 \\\text { B } & \text { E } & 90 & 99 & 108 \\\text { C } & \text { End } & 85 & 100 & 115 \\\text { D } & \text { F } & 19 & 25 & 31 \\\text { E } & \text { End } & 91 & 100 & 115 \\\text { F } & \text { End } & 62 & 65 & 68\end{array}\end{array} What is the estimated standard deviation in the time for activity E?


A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

C

Using the information given in the following table:  Activity  Precedes  Duration  Start  a, b, c  a  d 5 d  f 6 f  g 2 b  e 5 e  f 9 c  h 4 h  g, i 6 g  end 3 I  end 1\begin{array}{lll}\text { Activity } & \text { Precedes } & \text { Duration } \\\hline \text { Start } & \text { a, b, c } & - \\\text { a } & \text { d } & 5 \\\text { d } & \text { f } & 6 \\\text { f } & \text { g } & 2 \\\text { b } & \text { e } & 5 \\\text { e } & \text { f } & 9 \\\text { c } & \text { h } & 4 \\\text { h } & \text { g, i } & 6 \\\text { g } & \text { end } & 3 \\\text { I } & \text { end } & 1\end{array} (A) Identify the critical path. (B) Determine expected project duration.

Correct Answer

verifed

verified

(A) The critical pat...

View Answer

Which of the following are advantages of PERT? (I) It is visual. (II) It is automatically updated. (III) Activities that need to be watched closely can be identified.


A) I and II
B) II and III
C) III only
D) I and III
E) I, II, and III

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

Given the network diagram below, determine the probability that the project will finish within 26 weeks of its start. Times on the diagram are in weeks. Given the network diagram below, determine the probability that the project will finish within 26 weeks of its start. Times on the diagram are in weeks.

Correct Answer

verifed

verified

\(\begin{array}{lllll} \text { Path } & \text { Duration } & \text { Std. Dev. } & z & \text { Prob } \leq 26 \text { weeks } \\ \hline 1-2-5-7 & 25.00 & 2.45 & 0.41 & 0.6584 \\ 1-4-7 & 11.67 & 1.00 & 7.33 & \approx 1.00 \\ 1-3-6-7 & 19.33 & 1.63 & 4.08 & \approx 1.00 \end{array}\)

Which of the following is not a form of risk reduction in project management?


A) backup system
B) outsourcing
C) risk sharing
D) scenario analysis
E) selection analysis

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B, C  A  D 385062 B  E 9099108 C  End 85100115 D  F 192531 E  End 91100115 F  End 626568\begin{array}{l}\begin{array} { c c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B, C } & - & - & - \\\text { A } & \text { D } & 38 & 50 & 62 \\\text { B } & \text { E } & 90 & 99 & 108 \\\text { C } & \text { End } & 85 & 100 & 115 \\\text { D } & \text { F } & 19 & 25 & 31 \\\text { E } & \text { End } & 91 & 100 & 115 \\\text { F } & \text { End } & 62 & 65 & 68\end{array}\end{array} What is the estimated expected (mean) time for project completion?


A) 100 days
B) 140 days
C) 199 days
D) 200 days
E) 440 days

F) A) and B)
G) None of the above

Correct Answer

verifed

verified